A current transformer and a potential transformer do different jobs and are not interchangeable. The CT is threaded by the primary conductor and reproduces current; the PT is connected across the primary and reproduces voltage. An 11 kV incomer needs both, because every energy meter multiplies the two quantities and every protective function compares them.
The Two Devices Side by Side in an 11 kV Incomer
Take a normal 11 kV incomer feeding a 1250 kVA transformer. Full-load current is about 65.6 A, so the panel carries three CTs of 100/5 A around the phase conductors, and three PTs connected phase to earth in a voltage-transformer truck or as one three-phase unit. The two sets of instruments sit within a metre of each other and answer completely different questions.
The CT primary is the cable itself, one turn through the window. A 100/5 A ratio means twenty turns on the secondary, and the secondary current is fixed by the primary current, not by what is connected to it, until the core saturates. The PT is the reverse: a primary winding of many turns connected between phase and earth, a ratio of about 6350 V to 63.5 V on an 11 kV system with a 110 V secondary, and an output that holds its rated voltage as long as the connected burden stays inside the rated volt-amperes.
That single distinction, current source against voltage source, explains almost every rule that follows about wiring, fusing, earthing, burden and testing. It is also the reason a buyer cannot substitute one device for the other when a panel is short of space or a drawing is being value-engineered.
Series and Parallel: The Connection Decides the Failure Mode
The CT is a series device. Its primary is the line, and its secondary feeds a low-impedance loop of relay coils, meter coils, terminals and cable. The closer that loop is to a short circuit, the more accurately the CT works, which is why a CT secondary must never be opened under load and why a fuse is never fitted in it. Opening the secondary collapses the flux, the primary current continues to flow, and a high voltage appears across the terminals, limited only by saturation. Test terminal blocks that short the secondary before they break the circuit exist for exactly this reason.
The PT is a parallel device. Its primary spans phase to earth or phase to phase, and its secondary feeds a high-impedance loop of voltmeter and relay voltage coils. A short on a PT secondary is a fault current, cleared by the secondary miniature circuit breaker or the primary fuse, and it is the PT failure mode that damages hardware. Secondary earthing is equally specific: one point, normally at the terminal block near the transformer, never at both the transformer and the panel.
The wiring follows the same logic. CT secondary cable is sized by burden in volt-amperes and is commonly 2.5 to 6 mm² because the load current is 5 A or 1 A and the loop resistance matters. PT secondary cable is sized by permissible voltage drop, typically 1.5 to 2.5 mm², because the current is small and a 1 V error on a 100 V circuit is already one percent.
Eight Differences That Matter at the Specification Stage
The comparison below is the one worth pasting into a specification or a supplier comparison sheet. Each row is a decision the buyer has to make separately for the two devices.
| Item | Current transformer (CT) | Potential transformer (PT) |
|---|---|---|
| Connection | Series: the primary conductor passes through the core | Parallel: primary connected phase to earth or phase to phase |
| Primary quantity reproduced | Current, set by the load and the fault level | Voltage, set by the system |
| Standard secondary value | 5 A or 1 A at rated primary current | 100 V, 110 V, 100/√3 V or 100/3 V |
| Rated burden | Volt-amperes at rated secondary current (for example 15 VA at 5 A, equal to 0.6 Ω) | Volt-amperes at rated secondary voltage (for example 50 VA at 100 V, equal to 200 Ω) |
| Normal secondary state | Close to a short circuit | Close to an open circuit |
| Dangerous secondary state | Open circuit under load: high voltage, insulation failure, personnel risk | Short circuit: overcurrent in the winding, fuse or MCB operation |
| Accuracy expression | Ratio error and phase displacement for metering; composite error and accuracy limit factor for protection | Voltage ratio error and phase displacement; voltage factor for sustained overvoltage |
| Product standard | IEC 61869-2 | IEC 61869-3 |
Two rows are usually where a tender goes wrong. The burden row is quoted per core, not per transformer, and a CT with a metering core and a protection core has two separate figures. The worked CT burden calculation shows how quickly a long secondary run consumes that allowance. The accuracy row is not comparable between the devices: a 0.5 class CT and a 0.5 class PT are both called 0.5, but the limits and the current or voltage range over which they hold are defined by different clauses.
Why the Secondary Values Are Standardised at 5 A and 100 V
Relays, meters, transducers and test sets are built around a small set of inputs. On the current side that set is 1 A and 5 A; on the voltage side it is 100 V and 110 V line-to-line, with two derived values that appear on every residual circuit. Standardising the secondary means a protection engineer can test a panel with one injection set and a meter can be replaced without a new CT ratio.
The derived voltages are worth knowing before a drawing is approved. A PT with a 100/√3 V secondary gives 57.7 V phase to neutral, which is the value a relay expects when it measures phase voltage on a 100 V system. A residual winding with a 100/3 V secondary gives 33.3 V per phase, and three such windings connected in open delta produce about 100 V across the broken corner during a solid single-phase earth fault, which is the signal an earth-fault relay is set against.
| Secondary value | Where it is used | Practical note |
|---|---|---|
| 5 A CT secondary | Standard panels with short secondary runs | Lead burden rises with the square of current; 5 A suits runs up to roughly 50 m |
| 1 A CT secondary | Long runs, remote relay panels, retrofit cable trays | Five times the turns and a higher open-circuit voltage; relays must be ordered for 1 A |
| 100 V or 110 V PT secondary | Line-to-line voltage, voltmeters, over/under-voltage relays | 110 V is common where the local utility practice follows British convention |
| 100/√3 V PT secondary | Phase-to-neutral voltage, three-phase five-limb units | 57.7 V per phase on a 100 V base |
| 100/3 V residual winding | Open delta for earth-fault detection | Three windings sum to about 100 V on a solid earth fault |
The CT Saturates, the PT Does Not Behave That Way
A CT is limited by its core. During a fault with a DC offset, or after a heavy fault has left remanence in the core, the flux density climbs and the secondary stops reproducing the primary waveform. The relay then sees a distorted and reduced current, and it operates later than its settings say, or not at all. This is why protection cores are specified with an accuracy limit factor and why differential schemes on important feeders move to a class PX or TPS transformer with a declared knee point, magnetising current and secondary resistance.
A PT is limited by its insulation and its voltage factor. It does not saturate in normal service; its problems are sustained overvoltage on an unearthed system, ferroresonance with cable capacitance, and a primary fuse that either fails to clear a PT fault or operates on energisation inrush. The voltage factor, typically 1.2 continuous and 1.9 for a stated time on an effectively earthed system, is not a marketing figure, it is a requirement to be written into the datasheet and verified on the type test report.
At commissioning the checks divide along the same line. For the CT: ratio, polarity, secondary burden measurement and a primary injection test through the whole loop. For the PT: ratio, polarity, secondary earthing at one point, and a voltage check against a known source before the relay settings are loaded. The current transformer basics guide sets out the same checks from the construction side.
Accuracy Is Written Differently on the Two Nameplates
A metering CT marked 0.2S or 0.5 holds its error from a low percentage of rated current up to 120 percent, which is what a load-varying feeder needs. The S suffix is the part that matters for a tariff meter: without it, the class only promises accuracy near rated current, and a lightly loaded feeder spends its life outside the guaranteed band. A protection CT marked 5P20 holds five percent composite error up to twenty times rated primary current, and the twenty is only true at the stated burden.
A PT has no equivalent of the accuracy limit factor. Its nameplate carries a voltage ratio, one or more accuracy classes with their rated burdens, a thermal burden limit and a voltage factor, and the metering class is only guaranteed within a stated voltage range around rated voltage. That is why a 0.2 class PT is specified for a tariff point and a 3P unit for a protection point, and why the two duties should not share one winding.
- Metering core: 0.2S or 0.5, 10 to 15 VA, dedicated to the meter and the data logger.
- Protection core: 5P20 or 10P20, 15 to 30 VA, dedicated to the relay, with the ALF checked against the maximum through-fault current.
- Residual path: a core or a cable core-balance CT sized for earth-fault sensitivity, not for load current.
- Voltage side: 0.2 or 0.5 class metering winding and a 3P protection winding, or two separate PTs where the panel layout allows.
Why the Panel Needs Both, Not One or the Other
An energy meter does not measure current or voltage, it measures the product of the two over time. Remove the PT and the meter has no voltage reference; remove the CT and it has no current signal. The same logic governs protection. An overcurrent relay needs current, but a directional element, an undervoltage element, a distance element and a synchronising check all need voltage, and an earth-fault element needs either a residual connection of three CTs or a dedicated core-balance transformer.
There is a second, commercial reason to keep both duties properly instrumented. Fault level studies, protection coordination and loss calculations all depend on measured current and measured voltage, and a panel that is instrumented for one but not the other cannot be commissioned without temporary equipment. On a utility or EPC project that temporary equipment is a scope item, a test report and a delay. The potential transformer overview covers the voltage side in more detail, including the difference between a PT and a power transformer.
Where the two devices share a compartment, as in a combined metering unit, they still keep separate magnetic circuits. A combined CT/PT unit is a packaging decision, not an electrical one, and each part keeps its own ratio, class, burden and standard. The current transformer and the voltage transformer are specified separately for that reason, even when both are ordered for the same panel.
Selection Mistakes and What They Cost on Site
The errors below are common enough to appear in almost every tender review, and each one has a cost that lands after the panel has left the factory.
- One CT core shared by meter and relay. The meter sees every fault current and the class is wrong for at least one of the two duties. The fix is a second core at the order stage; after delivery it is a new CT and a repeat primary injection test.
- CT ratio taken from transformer capacity with no margin check. A 100/5 CT on a 65 A load reads two thirds of rating at full load, and the accuracy at light load suffers. Too large a ratio is a metering error that runs for years before anyone reconciles the bill.
- Voltage factor left out of the PT datasheet. On an unearthed or resonant-earthed system the PT sees sustained overvoltage during an earth fault. A unit ordered without the right factor fails early, and the failure is usually diagnosed as a quality problem rather than a specification problem.
- 1 A CT wired to 5 A relay inputs. The relay sees one fifth of the primary current and the settings are wrong by a factor of five. It is caught at commissioning, but only after the settings have been calculated and the test sheets written.
- ALF and burden omitted from the RFQ. The supplier delivers a CT that meets the ratio and the class but saturates earlier than the coordination study assumed. Replacing it means new CTs, new test reports and a second site visit.
- PT secondary earthed at both ends. A circulating current appears in the secondary circuit, fuses operate without a fault, and the cause is a drawing detail rather than a device failure.
What to Write Into the RFQ
A CT and a PT enquiry use different fields, and mixing them is the fastest way to receive a quotation that cannot be compared with the others. The table below is written for the 11 kV incomer used throughout this article and can be trimmed to any voltage class.
| Field | CT entry for the 11 kV incomer | PT entry for the same panel |
|---|---|---|
| System and insulation level | 11 kV nominal, 12 kV rated, indoor | 11 kV nominal, 12 kV rated, indoor |
| Ratio | 100/5 A, with the next ratio up stated as an alternative | 11000/√3 : 110/√3 V |
| Class and cores | 0.5 metering core plus 5P20 protection core | 0.5 metering winding plus 3P protection winding |
| Rated output | 15 VA per core, stated per core | 50 VA metering, 30 VA protection |
| Short-circuit or voltage factor | Short-time thermal current and dynamic rating, for example 25 kA for 1 s | Voltage factor 1.2 continuous, 1.9 for 8 h |
| Installation | Bushing or window type, bore size, panel fixing centres | Three single-phase units or one three-phase unit, fuse arrangement |
| Tests and documents | Type test reports, routine test report, ratio and polarity record | Type test reports, routine test report, ratio and polarity record |
| Standard | IEC 61869-2 | IEC 61869-3 |
Two sentences in the enquiry save most of the follow-up. State that the burden figures are per core and that the accuracy limit factor applies at that burden. State that the PT voltage factor applies for the earthing arrangement of the system, and name the arrangement. Suppliers quote what is written, not what is implied by the single-line diagram.
For panels where space is the constraint, the bushing form is often the practical answer on the current side: a bushing-type current transformer in the 100 to 600 A slips over an existing bushing or cable termination and removes the need for a separate bar primary. The trade-off is that the bore and the bushing diameter have to be confirmed before the panel is drilled, which is a drawing check rather than an electrical one.
Where Nahu Group Fits
Nahu Group manufactures current transformers and voltage transformers for medium-voltage distribution, including indoor and outdoor CTs, bushing and through-core types, split-core units for retrofit, and epoxy-cast PTs in single-phase and three-phase forms. Both families are built to IEC 61869, and a panel can be equipped from one supplier with the metering and protection cores kept separate. Send the single-line diagram, the system voltage and earthing arrangement, the CT ratio with class and burden per core, the PT ratio with class, burden and voltage factor, the panel type and the quantity. That is enough to return a configuration and the drawings for approval. Ask for the type test reports for the specific model, not for the family, and check that the report covers the ratio and burden you are ordering. Where the panel is a retrofit, send the existing bushing or cable diameter as well, since the bore dimension decides whether a bushing-type CT will fit.
Frequently Asked Questions
Can a potential transformer be used to measure current?
No. A PT is connected in parallel and its output is a voltage proportional to system voltage, so it carries only its own exciting and burden current. Connecting a PT in series with a load would put its high-impedance primary in the current path and produce a voltage drop, not a measurement. Current measurement needs a CT or a shunt, with the secondary closed through a low-impedance burden.
Why must a CT secondary never be open-circuited?
With the secondary open, the CT cannot produce the opposing ampere-turns, so the whole primary current becomes magnetising current and the flux drives deep into saturation. A high voltage appears across the open terminals, high enough to break down insulation and to injure anyone touching the circuit. Short the secondary at a test block before opening the loop, and never fit a fuse in a CT secondary.
What secondary voltage does a PT give on an 11 kV system?
For a phase-to-earth connected PT on an 11 kV system, the usual secondary is 110/√3 V, giving about 63.5 V phase to neutral and 110 V between phases on the secondary side. A 100 V basis is equally common, with 100/√3 V per phase and 100 V line to line. Relays and meters must be ordered for the value printed on the nameplate.
Do metering and protection need separate CT cores?
They should be separate. A metering core is optimised for accuracy at normal load and is specified with a class such as 0.2S or 0.5, while a protection core is optimised for faithful reproduction during faults and carries an accuracy limit factor. Sharing one core forces a compromise on both duties and exposes the meter to fault currents. Two cores in one housing cost far less than a replacement CT and a repeat commissioning test.
What does 5P20 mean on a CT nameplate?
The 5P is the protection class, allowing five percent composite error, and the 20 is the accuracy limit factor: the CT holds that error up to twenty times its rated primary current, provided the connected burden does not exceed the rated burden. A 100/5 A, 5P20, 15 VA CT is therefore specified to remain usable up to about 2000 A primary into 15 VA.
Can one PT supply both metering and protection?
It can physically, but it should not be the design. A metering winding is specified for accuracy near rated voltage and a protection winding for behaviour during voltage collapse and earth faults, and the two duties have different burden and voltage factor requirements. Where only one PT is available, specify two secondary windings with separate classes and separate fuses, and keep the wiring in separate multicores.
Sources and Further Reading
- IEC 61869-2 — Instrument transformers, Part 2: Additional requirements for current transformers — ratios, burden, accuracy classes and the 5P/10P protection limits referred to above.
- IEC 61869-3:2011 — Instrument transformers, Part 3: Additional requirements for inductive voltage transformers — the voltage factor, rated output and residual winding definitions used in the PT section above.
Published Nov 17, 2026 · Nahu Group (NAHU Electric Technology)