A potential transformer (PT) — called a voltage transformer (VT) in IEC terminology — is an instrument transformer that scales a high system voltage down to a standardized, safe low voltage, typically 100 V or 110 V at rated primary, for meters, protective relays and instrumentation. It is not a power transformer. A PT carries almost no load and exists only to reproduce the primary-voltage waveform accurately at a known ratio, which is why a 100 VA PT and a 100 kVA transformer are different machines despite both having windings.
That single sentence answers most "what is a potential transformer" questions: it is a measurement device, not an energy-transfer device.
What a Potential Transformer Actually Does
Four jobs define the device, and the fourth is what separates it from everything else in the substation.
- Steps the voltage down at a fixed ratio. A 11 kV system uses a ratio such as 11000/√3 : 100/√3 V, so the secondary stays at the standardized value whatever the primary.
- Galvanically isolates the network from the instruments. The metering and protection equipment never touches the high-voltage conductor.
- Delivers a standardized secondary. Because the secondary is fixed by standard, a meter or relay is interchangeable between installations.
- Holds the ratio error inside an accuracy class. It does this only because its burden — the load it drives — is kept tiny.
The voltage transformer covers the indoor and outdoor builds used from 12 kV up to sub-transmission voltages.
Potential Transformer vs Power Transformer: The Three Real Differences
| Property | Potential (voltage) transformer | Power transformer |
|---|---|---|
| Purpose | Reproduce voltage accurately for measurement and protection | Transfer active and reactive power |
| Rated power | Tens of VA (e.g. 30, 50, 100 VA) | kVA to MVA |
| Accuracy | Held to class 0.2 / 0.5 (metering), 3P / 6P (protection) | Not ratio-accuracy rated |
| Burden it drives | Near-zero, tightly specified | Full rated load |
| Cooling | Natural convection, no forced cooling | Oil, ONAN/ONAF, often forced |
| Failure mode of concern | Ratio drift, phase error, core saturation | Thermal, dielectric breakdown under load |
The headline difference buyers care about is the first row: capacity. A PT is rated in VA because it is designed to drive almost nothing. A power transformer is rated in kVA because driving load is its whole job. The accuracy row is the second: a PT is certified to a ratio class; a power transformer is not.
How a PT Is Built: Electromagnetic, Capacitive, Electronic
- Electromagnetic (inductive) VT. A wound transformer, the common choice from 12 kV to around 36–72 kV. Simple, accurate, and the type shown throughout this article.
- Capacitive VT (CVT). A capacitor divider plus a small electromagnetic unit. Above roughly 72.5 kV it is cheaper than a wound unit, and the same divider can feed a line-carrier coupling device.
- Electronic (non-conventional) VT. A voltage sensor with a converter, standardized under IEC 61869-10 and IEC 61869-11 for digital substations using IEC 61850 sampled values.
For the 12–36 kV networks most NAHU customers run, the electromagnetic unit dominates. The JDZX11-20 and JSZV12-10R are representative indoor builds.
Accuracy Classes and Burden — Why They Decide the Rating
Accuracy is expressed two ways and both matter. IEC 61869-3 defines metering classes 0.1, 0.2, 0.5 and 1.0, and protection classes 3P and 6P. Each class sets a limit on ratio error and phase-displacement error, but only at the rated burden and below it. Burden is the total load — meters, relay coils, wiring — expressed in VA at a stated power factor, usually 0.8 inductive.
| Application | Typical class | What goes wrong if burden is wrong |
|---|---|---|
| Revenue metering | 0.2 or 0.5 | Oversized burden → ratio error → billing dispute |
| Protection (distance, overvoltage) | 3P or 6P | Under-burdened → saturation on fault → slow or wrong trip |
| General indication | 1.0 or 3.0 | Less critical, but still bounded by class |
A PT specified without its connected burden is a PT that may pass the factory test and fail in service. State the burden the secondary must support, not just the ratio.
Sizing a PT for a Metering or Protection Circuit
Sizing is mostly burden accounting, and the steps are the same whether the PT feeds a meter or a relay.
- Add the burden of every connected device — meter, relay, transducer, and the wiring (long secondary runs add VA fast).
- Keep the actual burden between about 25% and 100% of the rated burden; a PT driven far below its rating still meets class, but one driven above it does not.
- Choose the class against the job: 0.2 / 0.5 for metering, 3P for protection.
- Fuse the primary for fault clearing, and earth exactly one secondary terminal so a primary-to-secondary fault cannot raise the secondary to system potential.
Where the PT sits with current transformers in a common enclosure, see the high-voltage metering boxes; the same burden rules apply to the CTs, covered in the current transformer guide.
Where Potential Transformers Sit in the Substation
A PT appears wherever a voltage has to be measured safely: incoming feeders, busbar sections, metering cabinets and ring main units. On a three-phase system the usual arrangement is three single-phase VTs for the phase-to-phase and phase-to-earth voltages, plus an open-delta (V-V or broken-delta) connection to derive the residual (zero-sequence) voltage for earth-fault detection. Single-phase units are preferred because one spare covers every position.
What to Write Into the RFQ
| Parameter | Text to put in the specification |
|---|---|
| Ratio | Primary / secondary voltage, e.g. 11000/√3 : 100/√3 V, single or three-phase |
| Class | Metering 0.2 or 0.5, protection 3P; name both if the unit serves both |
| Burden | Rated burden in VA at cos φ 0.8, and the actual connected burden |
| Insulation level | Rated voltage, power-frequency and impulse withstand per IEC 60071 |
| Frequency | 50 Hz or 60 Hz — a 50 Hz unit on a 60 Hz system is wrong |
| Mounting | Indoor epoxy-cast, outdoor, or in a metering box / RMU |
| Earthing | One secondary terminal earthed; state which |
Frequently Asked Questions About Potential Transformers
What is the difference between a potential transformer and a power transformer?
A potential transformer is an instrument transformer rated in tens of VA that reproduces the primary voltage accurately at a fixed ratio for meters and relays. A power transformer is rated in kVA or MVA and exists to transfer energy. The PT is held to a ratio accuracy class; the power transformer is not.
What is the standard secondary voltage of a potential transformer?
For IEC systems the standardized secondary voltage is 100/√3 V per phase on a 100 V line-to-line basis, or 100 V where a single-phase unit is used phase-to-earth. IEEE practice in North America commonly uses 120 V. The secondary voltage is fixed by standard, not by the primary.
Why does a PT secondary have to be grounded?
One secondary terminal is earthed so that, if the primary-to-secondary insulation fails, the low-voltage side cannot rise to system potential. A single earthing point only — a second earth creates a parallel path that distorts the ratio and can mask a fault.
What PT accuracy class do I need for metering?
Metering normally uses class 0.2 or 0.5 under IEC 61869-3, while protection uses 3P or 6P. Pick the class against the connected burden: the actual burden should sit between roughly 25% and 100% of the rated burden, otherwise the ratio and phase-angle error grow beyond the class limit.
When is a capacitive voltage transformer used instead of a wound PT?
Above about 72.5 kV the capacitor divider of a capacitive voltage transformer is cheaper than a wound electromagnetic unit and the same divider can feed a carrier-coupling device. Below that, wound inductive VTs are simpler and more accurate, so they dominate the 12 to 36 kV range.
Sources and Further Reading
- IEC 61869-3:2011 — Instrument transformers, Part 3: Additional requirements for inductive voltage transformers — accuracy classes, burdens and the routine tests that prove a PT meets its class
- IEC 61869-1:2009 — Instrument transformers, Part 1: General requirements — the common definitions, rated values and test rules for VTs and CTs
- IEEE C57.13 — Standard for Instrument Transformers — the North American rating, accuracy and burden basis for VTs and CTs