A switchgear test list has two halves that answer two different questions. Factory routine tests prove the assembly was built the way the type-tested design was approved; site acceptance tests prove that transport, foundation work and cable termination did not undo it. The mistake buyers make is treating the first as paperwork and the second as a formality — the failures that delay energisation almost always sit in the gap between them.

IEC 62271-200 is the reference for the assembly, IEC 62271-1 for the common clauses, and every item below should appear in the submittal with a value, a judgement criterion and a signature. An item without a criterion is not a test; it is an observation.

Factory Routine Tests: What Must Be Proven Before Dispatch

Routine tests are performed on every unit, not on a sample. For a metal-enclosed or metal-clad assembly the list below is the minimum a buyer should see in the factory test report, with the measured value recorded against each item.

Two commissioning technicians working with test equipment in a substation yard beside transformer and switchgear installations
TestPurposeJudgement on the report
Power-frequency dielectric test, main circuitProves insulation clearances and busbar support insulation survive the specified voltageApplied voltage and duration (1 min) stated; no breakdown or flashover; test voltage matches the rated insulation level
Dielectric test, auxiliary and control circuitsFinds wiring damage and clearance faults in the secondaryVoltage applied to the whole auxiliary circuit, wiring disconnected from sensitive devices where required
Main circuit resistanceFinds loose joints, undersized contact pressure and bad busbar connectionsValue per phase in micro-ohms, compared with the type-test or design value; phase-to-phase spread within the stated tolerance
Mechanical operation testProves the mechanism, interlocks and indicators work after assemblyNumber of close/open cycles stated; interlocks demonstrated, not just present
Wiring and secondary continuityCatches wrong terminal numbers and crossed cores before they become commissioning faultsPoint-to-point check against the approved schematic, signed by the tester
Instrument transformer ratio and polarityConfirms the CT and VT match the rating plate and the drawingMeasured ratio and polarity per core; metering and protection cores clearly separated
SF6 tightness and gas densityDetects seal defects that would otherwise surface after energisationLeakage expressed per the standard method; density switch alarm and lockout settings recorded
Partial discharge, where specifiedFinds insulation defects that a withstand test leaves alivepC value with the pre-stress voltage stated; a pC number without a voltage means nothing
Protection relay settings and injectionConfirms the relay is set to the study and trips the right breakerSetting sheet revision, injection results per stage, trip and alarm contacts verified

Two items on that list are frequently subcontracted and then reported as if they were done in-house: partial discharge and relay injection. Ask which laboratory performed the test and see the calibration certificate for the instrument. Where the breaker itself is tested — timing, travel, vacuum integrity — the sequence is set out in the vacuum circuit breaker testing procedure, and the cores behind the ratio figures are described on the current transformer range.

What Each Factory Test Actually Detects

KYN28A-12 switchgear cabinets and trucks lined up on the workshop floor ahead of routine testing

A test list is only useful if the buyer knows which defect each item catches. Otherwise a report full of "OK" tells you nothing about the unit you are about to energise.

DefectTest that finds itWhat it costs if missed
Metal particle or void left in cast resinPartial dischargeFlashover weeks after energisation, with the feeder out and the unit to be replaced
Loose busbar joint or under-torqued contactMain circuit resistanceHot joint, thermal damage, unplanned outage in the first summer
Wrong CT ratio or reversed polarityRatio and polarity testProtection misoperates or metering under-reads for years
Interlock that blocks the wrong operationMechanical operation and interlock testOperator works around the interlock, or cannot restore supply after a fault
Damaged secondary core during wiringAuxiliary dielectric and continuityTrip circuit fails on the one operation that matters
Slow SF6 leak at a sealTightness testGas top-ups and a lockout at the worst moment; possible derating

Site Acceptance: What Changes Once the Unit Is Installed

On site the unit has been transported, lifted, bolted to a foundation, connected to cables and had its secondary wiring run to a panel. Each of those steps can undo a factory result, so the site list tests the interfaces rather than repeating the factory.

Site testWhat it provesJudgement criterion to write down
Visual and mechanical inspectionThe unit arrived intact and is installed as drawnNo transit damage, correct clearances, gland plates and cable boxes sealed, torque marks intact
Insulation resistance, main circuitNo moisture, dust or cable-termination damageValue recorded per phase against the delivery value and the utility minimum; a large drop between visits is the finding
Insulation resistance and continuity, secondaryWiring survived the pull and the terminations are soundContinuity per core, no cross-connection, IR above the figure agreed with the utility for control wiring
CT and VT secondary checksThe instrument transformers still match the drawing after cable workRatio and polarity re-checked at the terminals that feed the relay and the meter
Protection injection at the panelThe complete trip path works, not just the relayRelay picked up, trip coil operated, breaker tripped, alarm and event recorded with timestamps
Interlock and earthing switch operationThe safety mechanism works in the installed conditionEvery blocked operation demonstrated as blocked; earthing switch closed and opened with the correct status indication
Gas density and dew point, SF6 unitsThe gas system is sound after transport and top-upPressure and dew point within the manufacturer's filling values, alarm and lockout verified by simulation
Cable tests where specifiedThe cable and its terminations, not the switchgear, are soundTest method, voltage and duration per the cable standard; results kept with the switchgear record

How to Write a Judgement Criterion That Holds Up

Most disputes at inspection are not about whether a test was done but about what number was acceptable. Three rules make a criterion defensible: tie it to a reference the supplier cannot move (the type test report, the standard clause or the utility specification), state the condition under which the value applies (temperature, pre-stress voltage, test duration), and say what happens when the value is missed — retest, replace or accept with a deviation.

  • For dielectric tests, quote the rated insulation level from the type test report rather than a remembered figure.
  • For resistance and insulation measurements, record the ambient and the instrument, because both change the number.
  • For partial discharge, state the pre-stress voltage and the pC limit together; the pair is the criterion, not either alone.
  • For protection, state the injection point — relay terminals or primary — because the two prove different things.

Where partial discharge matters, the interpretation is a subject in itself; the partial discharge testing guide explains what the measurement actually shows and where it is misread.

Where Test Lists Fail at Inspection

  • Values without conditions. An insulation resistance figure with no temperature and no instrument cannot be compared with anything, including the same unit next year.
  • Reports without serial numbers. If the report does not carry the unit serial and the drawing revision, it proves nothing about the equipment delivered.
  • Copied type-test values in a routine report. Identical numbers across several units are a warning sign, not reassurance.
  • Interlocks "checked" by inspection only. The interlock has to be operated and shown to block the wrong action.
  • Arresters and instruments left connected during insulation tests. The reading is then a statement about the arrester, not the switchgear.
  • No record of who tested and when. An unsigned report is not evidence, and a warranty claim without evidence is a negotiation you lose.

What to Ask For With the Equipment

Pole-mounted switchgear on a distribution crossarm with overhead conductors during a site inspection

The document set is part of the specification, not an afterthought. For a medium voltage assembly, the distribution cabinet range is configured to order, so the documents should be listed in the same enquiry as the ratings:

  • Type test report to IEC 62271-200, with the certificate body and the tested configuration identified — the type test report guide covers how to read it.
  • Routine test report per unit, with serial numbers, measured values, instrument identification and tester signature.
  • Interlock function record and the approved schematic revision it was checked against.
  • Protection setting sheet and injection record, with the study revision quoted.
  • Gas filling values and dew point, plus the density switch settings, for SF6 assemblies.
  • Outline and foundation drawings, cable entry details, and the earthing terminal arrangement.
  • Packing list and transit damage procedure, agreed before dispatch rather than after arrival.

Where Nahu Group Fits

Nahu Group builds medium voltage switchgear for 12 kV and 40.5 kV systems — metal-enclosed ring main units, armored metal-clad withdrawable gear and fixed panels — air insulated, for indoor substations and distribution rooms, with protection, metering and interlocking per the single line diagram. Each unit ships with its routine test record against the serial number.

To get a test plan matched to your specification, send the single line diagram, the system and highest system voltage, the fault level and duration, the protection scheme and the utility's acceptance clauses. We will return the routine test list, the site acceptance checklist and the document package index before the order is placed, so that nothing in the list arrives as a surprise at inspection. Breaker-level timing and travel records are covered under the vacuum circuit breaker range.

Frequently Asked Questions About Switchgear Testing

What is the difference between a routine test and a type test?

A type test is done once on a representative design to prove the design meets the standard; a routine test is done on every unit to prove it was built like the tested design. A routine test report without a type test behind it proves the unit works, not that it is qualified for the fault level and insulation level you specified.

Which tests must be repeated on site?

Only the ones that installation can invalidate: insulation resistance, secondary continuity, instrument transformer checks, protection injection, interlock operation and gas tightness. Repeating the full factory dielectric test on site is neither practical nor required; what matters is proving that transport, foundations and cable work did not damage what the factory proved.

What insulation resistance value is acceptable?

There is no single number that fits every assembly. The defensible criterion is a value agreed with the utility for the voltage class, compared with the value measured at delivery, with the temperature and instrument recorded. A reading that halves between two visits matters more than whether it sits above a threshold.

Does a partial discharge test replace the power-frequency withstand test?

No. The withstand test proves the insulation survives the specified voltage for a minute; the partial discharge measurement finds defects that survive that minute and then fail in service. They answer different questions, and a specification that asks for only one of them leaves half the insulation risk unmeasured.

How long should the test records be kept?

For the life of the equipment. The routine test values become the baseline for every later measurement, including the comparison that tells you whether a joint is degrading. Utilities normally keep them with the asset register, and a buyer who does not receive them at handover has lost the reference point permanently.

Sources and Further Reading

Published Nov 6, 2026 · Nahu Group (NAHU Electric Technology)