What an accuracy class actually guarantees
A 0.2 class on a current transformer does not mean "0.2% accurate". It means the ratio error stays inside ±0.2% at 100% and 120% of rated primary current and the phase displacement stays inside ±10 minutes, at rated frequency, with any burden between 25% and 100% of the rated output. Outside those four conditions the class promises nothing, which is where most metering disputes begin.
Three definitions sit behind those figures and buyers mix them up constantly. Ratio error, also called current error, is (Kn × Is − Ip) / Ip expressed as a percentage, where Kn is the rated transformation ratio, Ip the actual primary current and Is the actual secondary current. Phase displacement is the angle between the primary current vector and the secondary current vector reversed, quoted in minutes because the angles involved are small. Composite error belongs to protection cores: it is the root-mean-square difference between the instantaneous primary current and the instantaneous secondary current multiplied by the rated ratio, taken over a steady-state cycle and expressed as a percentage of the rms primary current. The first two describe a measuring core, the third describes a protective one, and a single transformer can carry both.
In IEC 61869-2 the class number is the highest permissible percentage ratio error at rated primary current, qualified by the output and the burden range at which it holds. That is why the same CT can be sold as 0.5 at 10 VA and as 1 at 30 VA on the same core, and why comparing two quotations on class alone tells you almost nothing about which one will pass the utility's meter test.
The measurement classes from 0.1 to 1
The four standard measuring classes are specified at 5%, 20%, 100% and 120% of rated primary current. Read the row at the current where your load actually sits, not at the middle of the range: a feeder that runs at 15% of the CT rating most of the day spends its life in the column that is easiest to fail.
| Class | Ratio error ±% at 5% In | At 20% In | At 100% In | At 120% In | Phase ±min at 5% In | At 20% In | At 100% In | At 120% In |
|---|---|---|---|---|---|---|---|---|
| 0.1 | 0.4 | 0.2 | 0.1 | 0.1 | 15 | 8 | 5 | 5 |
| 0.2 | 0.75 | 0.35 | 0.2 | 0.2 | 30 | 15 | 10 | 10 |
| 0.5 | 1.5 | 0.75 | 0.5 | 0.5 | 90 | 45 | 30 | 30 |
| 1 | 3.0 | 1.5 | 1.0 | 1.0 | 180 | 90 | 60 | 60 |
Class 0.1 is a laboratory and calibration grade and rarely appears in a distribution panel. Class 0.2 and 0.5 cover tariff and check metering respectively in most utility practice, and class 1 is normally adequate for panel ammeters and indicating instruments where a 1% reading error changes no decision. The jump from 0.5 to 0.2 is a factor of two and a half in permitted error at rated current, but a factor of two at 5% current, which is the point where light-load revenue is actually lost.
Classes 3 and 5 sit outside this table and are specified in a separate part of the standard: ratio error ±3% and ±5% at 50% and 120% of rated current, with no phase displacement limit at all, and the limits hold only from 50% to 100% of rated output. A class 3 core is a coarse indication device. Putting one on a billing circuit is a specification error that a meter test will find and a commercial team will have to argue about. For tariff work the unit is chosen from the current transformer by ratio and core count first, and the class is fixed afterwards.
What the S adds, and why 1% decides the purchase
Design a 400/5 CT for a feeder whose peak is 380 A and whose overnight load is 6 A. The peak sits comfortably at 95% of rated current, so a class 0.2 core looks correct on the calculation sheet. Then notice that 6 A is 1.5% of rated current, and the class 0.2 limits are specified from 5% upwards, so the transformer has no guaranteed accuracy at the current it carries for eight hours a night. The S class exists to close that gap: its limits start at 1% of rated current and run to 120%.
The S row is the non-S row shifted one current step down, which is the cleanest way to remember it. Both 0.2 and 0.2S permit ±0.2% at 100% current; the difference is that 0.2S also permits only ±0.75% at 1% current, which is exactly what plain 0.2 allows at 5%.
| Class | Ratio error ±% at 1% In | At 5% In | At 20% In | At 100% In | At 120% In | Phase ±min at 1% In | At 5% In | At 20% In | At 100% In | At 120% In |
|---|---|---|---|---|---|---|---|---|---|---|
| 0.2S | 0.75 | 0.35 | 0.2 | 0.2 | 0.2 | 30 | 15 | 10 | 10 | 10 |
| 0.5S | 1.5 | 0.75 | 0.5 | 0.5 | 0.5 | 90 | 45 | 30 | 30 | 30 |
Two situations justify the S grade and one does not. It pays on a feeder with a large day-to-night ratio, and on any circuit where export or reverse flow is metered, because a factory that generates at midday can run at 2% of the CT rating at night. It does not pay on a fixed-load circuit running between 60% and 90% of rating all year; there the plain 0.5 class is honest and adequate.
The S grade is also the answer to a question that arrives late in procurement: what does the letter S stand for? The standard does not define it as an abbreviation. It marks the class whose error limits are specified over an extended current range starting at 1% of rated current, and that definition is the one to write into the datasheet, because a supplier who reads S as a marketing suffix will not test the 1% point.
Protection classes: 5P10, 5P20 and 10P20
A protection core is not specified by accuracy at rated current. The number before the P is the maximum composite error at the rated accuracy limit primary current, and the number after the P is the accuracy limit factor, the multiple of rated primary current at which that error is measured. Standard accuracy limit factors are 5, 10, 15, 20 and 30, and the standard protection classes are 5P and 10P.
| Class | Composite error at rated accuracy limit primary current | Ratio error at rated primary current | Phase displacement at rated primary current | Typical use |
|---|---|---|---|---|
| 5P10 | 5% at 10 × In | ±1% | ±60 min | Feeder overcurrent, small transformer incomer |
| 5P20 | 5% at 20 × In | ±1% | ±60 min | Feeder and busbar protection with a high fault level |
| 10P20 | 10% at 20 × In | ±3% | No limit specified | Overcurrent stages where a loose replica is acceptable |
| 5PR / 10PR | 5% / 10% at the stated factor | ±1% / ±3% | ±60 min / no limit | Low-remanence cores for schemes sensitive to remanent flux |
At 20 times rated current the core is far into saturation by design, and a 5% composite error is the promise that the relay still receives a usable replica of the fault. That is all the relay needs in order to decide. It is not a metering grade and it must never be used as one, which is a recurring mistake when a combined core order is written as 0.2S/5P20 and the two cores are then connected the wrong way round on site.
Two consequences follow from the definitions. First, 5P20 is not "better" than 5P10 in the abstract; it covers a higher fault level, and if the prospective fault current at the installation is 8 kA on a 600/5 CT, a 5P10 core already reaches 6 kA of accuracy limit current while the 5P20 reaches 12 kA. Second, the composite error figure cannot be compared with a metering class number, because composite error is measured with the core saturating while ratio error is measured with it linear. When a differential scheme needs a defined knee point and a defined secondary resistance instead of a composite error promise, the specification belongs to the PX class, as set out in why a class PX core is written differently from a 5P core.
Reading 600/5 A, 5P20, 15 VA as one sentence
Those three fields only mean something together. A 600/5 A ratio is 120:1. An accuracy limit factor of 20 puts the rated accuracy limit primary current at 12 kA. Fifteen VA at a power factor of 0.8 inductive is the burden the core was tested into. So the line reads: up to 12 kA of primary current, driving no more than 15 VA of secondary loop at 0.8 lagging, the secondary current will not depart from one hundred and twentieth of the primary by more than 5% composite error, and at rated current the ratio error will stay inside 1% with 60 minutes of phase displacement.
Run the same sentence for a metering core and the arithmetic changes shape. A 400/5 A, 0.2S, 10 VA core with an instrument security factor of 10 promises ±0.2% from 80 A to 480 A and ±0.75% down to 4 A, at any burden between 2.5 VA and 10 VA, and it promises to saturate by around 4 kA so that a through fault does not destroy the meter. Drop the FS from the order and the last promise disappears, which is why a metering core without a stated security factor is an incomplete specification, not a small omission.
The secondary current at the accuracy limit is worth knowing at commissioning: 12 kA primary through a 600/5 core is 100 A in the secondary circuit. Most primary injection sets cannot reach that, which is why the type test report rather than a site test is usually the evidence a utility accepts.
Where the class stops applying
The burden window is the first limit and the most commonly breached. Measuring classes hold their limits from 25% to 100% of rated output, classes 3 and 5 only from 50% to 100%, and protection classes at rated burden. Rated output values are 2.5, 5, 10, 15 and 30 VA, with higher values available by agreement. The rated burden carries a power factor of 0.8 inductive, except that below 5 VA a power factor of 1.0 applies with 1 VA as the floor.
That window is a two-sided constraint, and the low side is the one engineers forget. A 30 VA core ordered for a loop that draws 4 VA is running below a quarter of its rated output, and the standard does not promise its class there. If the loop genuinely is light, the correct move is a smaller rated output rather than a larger one, or the extended burden range option, where the limits hold from 1 VA up to rated output at unity power factor with rated output capped at 15 VA.
The second limit is the current range itself. The standard value of rated continuous thermal current is the rated primary current, and where a higher figure is needed the preferred values are 120%, 150% and 200%, marked as an extended current rating. A measuring core may carry an extended current rating only if its rated continuous thermal current equals the extended primary current and the 120% error limits are retained all the way up to it. A nameplate that says 120% without either of those two conditions being met is a thermal claim, not an accuracy claim.
The third limit is per core. A three-core CT carries three independent classes, three rated outputs and often three different ratios on one primary, and the nameplate will print them as one string. In NAHU's LZJC-10 indoor current transformer, for example, the published table gives 10 VA on the 0.2S and 0.5S cores and 15 VA on the 10P10 and 10P15 cores, so the same transformer is a 10 VA device for metering and a 15 VA device for protection. Reading one VA figure off the front plate and applying it to all cores is how a correct transformer gets rejected at the meter test. A post-type unit such as the LZZBJ9-10 indoor current transformer is offered with single, double or combined classes across a 5 A to 3,000 A primary range for exactly that reason.
The fourth is the secondary loop outside the transformer, which the CT cannot control. Lead resistance adds directly to the burden, and a long run of 2.5 mm² cable can consume the whole margin between the rated output and the actual loop. The arithmetic for that belongs with the burden calculation itself, in the VA budget and lead-size worked example, and it has to be settled before the class is fixed rather than after.
Selection mistakes and what they cost
The mistakes below recur in enquiries and each one has a commercial price attached, usually paid after energisation rather than before shipment.
- 0.2 specified where 0.2S was needed. On a feeder with a large day-to-night ratio the light-load hours fall outside the specified range, so the meter is lawful but unverified where the energy is cheapest and least supervised. The cost appears at the annual reconciliation, when the discrepancy has to be explained against a class that never covered those hours.
- Class quoted without a rated output. A 0.2S core at 10 VA in a loop that needs 15 VA is out of class at 20% load, not at full load, so the error hides in exactly the operating region the S grade was bought to protect. Rework means new cores, new test certificates and a repeat meter test.
- Protection class used for a differential scheme. Composite error at the limit current says nothing about behaviour at the knee, so the scheme is left without the parameter it actually depends on. The correction is a new core type, not a relay setting.
- Instrument security factor left off a metering core. Nothing in the order forces the core to saturate during a through fault, and the meter becomes the fuse. This one is recovered as an instrument failure and an outage, not as a warranty claim on the CT.
- 5P20 chosen because it reads as the largest number. Where the prospective fault current is 8 kA on a 600/5 core, the extra range buys nothing and can cost core size and winding resistance, which then changes the burden and the lead calculation downstream.
None of these are manufacturing defects, so routine tests on the transformer will not catch them. The only defence is a datasheet that states class, rated output, burden power factor, current range and security or limit factor as one requirement rather than five preferences.
What to write into the RFQ and the datasheet
An enquiry that returns the right transformer first time is written as a requirement list: every field below is stated, and the supplier's only freedom is the model that meets it.
| Field | What to state | What goes wrong if it is left open |
|---|---|---|
| Ratio and rated currents | Rated primary current from the load study, rated secondary current 1 A or 5 A, and any multi-ratio taps required | The supplier applies a default ratio and the metering multiplier no longer matches the meter |
| Cores and class per core | Number of cores, and for each one the class: 0.2S or 0.5S for metering, 5P or 10P with the accuracy limit factor for protection | One class is quoted for a multi-core unit and the wrong core is wired to the meter |
| Rated output per core | VA for each core separately, with the burden power factor, normally 0.8 inductive | A single VA figure is applied to all cores and the metering core runs outside its window |
| Security and limit factors | Instrument security factor, normally FS 5 or FS 10, on metering cores; accuracy limit factor on protection cores | The metering core has no defined saturation point and the protection core no defined limit current |
| Current range | Rated continuous thermal current, and whether an extended current rating of 120%, 150% or 200% is required | A standard thermal rating is supplied into a circuit that carries more than rated current continuously |
| Short-time ratings | Rated short-time thermal current in kA for 1 s, and rated dynamic current in kA | The core is sized for the ratio but not for the fault level, and the through fault is the last thing it sees |
| Insulation level | Highest voltage for equipment, power-frequency withstand and lightning impulse level for the system | A 12 kV unit is offered for a 24 kV system, discovered at the dielectric test |
| Frequency and mounting | 50 Hz or 60 Hz, indoor or outdoor, post, bar-primary or window type, and the panel interface dimensions | The ratio is right and the transformer will not fit the compartment it was bought for |
| Test evidence and documents | Type test report to IEC 61869-2, routine accuracy test record for the delivered unit, outline drawing for approval, packing list | The drawing arrives with the goods and the accuracy evidence never arrives at all |
The standard reference to put in the same document is IEC 61869-2, and the enquiry should ask the supplier to name the edition it tests to. Class limits have been stable for years, but the test and marking clauses have not, and a certificate that quotes no edition is hard to defend in a witness test.
One more sentence is worth adding to any order for a metering core: state that the quoted class applies across the burden range from 25% to 100% of rated output, and that the routine test record must show the measured ratio error at 1%, 5%, 20% and 100% of rated current. That single line turns the class from a catalogue adjective into a number someone has to produce.
Frequently asked questions
Is 5P20 better than 5P10?
It covers a higher fault level, not a tighter accuracy. Both permit 5% composite error, at 20 and 10 times rated primary current respectively. Choose the factor that exceeds the prospective fault current at the installation with margin, and check that the resulting core still fits the burden budget; a larger factor usually means a larger core and more secondary resistance.
Can a 5P20 core be used for metering?
No. A protection core is specified by composite error at a current many times rated, where it is saturating by design, and it carries no requirement over the light-load range where revenue is measured. Use a separate 0.2S or 0.5S core for the meter, and keep the two secondary circuits electrically separate all the way to the terminal block.
Does the S in 0.2S mean anything specific?
The standard does not define it as an abbreviation. It identifies the class whose limits are specified from 1% of rated current instead of 5%, and which therefore also covers the 120% point. In practice the S row is the non-S row shifted one current step down, so 0.2S at 1% matches 0.2 at 5%.
Does a higher VA rating make a CT more accurate?
It makes it capable of driving a heavier secondary loop at the stated class. VA is the burden the accuracy is guaranteed into, not a quality grade, and a 30 VA core used in a 4 VA loop is outside the standard's burden window on the low side. Match the rated output to the measured loop burden, with a margin for lead resistance.
Why does my 0.2S meter read high at light load?
Check three things in order: the actual secondary burden against the rated output, the lead resistance against the assumed cable length, and whether the routine test record actually shows the 1% and 5% points. A core tested only at rated current can carry a 0.2S label and still sit outside its limits in the range the meter cares about.
Which class should a check meter use?
0.5 or 0.5S is the usual choice for a check meter compared against a 0.2S tariff meter, because the comparison uncertainty stays well inside the dispute threshold. Use 0.2S for the tariff core itself, and never place the check and tariff functions on the same core, since a fault in one secondary circuit then removes both readings.
Published Nov 24, 2026 · Nahu Group (NAHU Electric Technology)