A medium voltage cable termination procedure runs six stages, and the finished set is judged on two of them: where the metallic screen was cut, and where the stress-control element sits on that cut. Strip lengths, earthing, crimping and testing can be corrected on site. A screen cut in the wrong place, or a tube that has already closed over it, cannot.

That asymmetry is what makes the procedure a procurement document rather than a fitter's habit. The kit drawing fixes the strip dimensions, the cable data sheet fixes the diameter, the panel drawing fixes phase spacing and the earth bar position, and the project specification fixes the test. A crew holding all four does not guess. A crew missing one of them guesses at the stage where guessing is most expensive.

What each stage of the procedure has to produce

Read the six stages as gates. Each one produces something the next stage depends on, and each one leaves a record that a third party can check without having watched the work. That is the difference between an installation that can be accepted on paper and one that has to be re-opened to be believed.

StageWhat it fixesWhat is checked before the next stage startsRecord left behind
1. Measure and stripInsulation, screen and oversheath strip lengths, taken from the kit drawingCable diameter measured at three points against the set's published window; strip marks scribed, not cut freehandMeasured diameter, kit serial number
2. Cut the screen, seat the stress controlThe field at the end of the screenCut square, insulation unscored, semi-conductive residue removed, element on its reference markPhotograph of the cut before the tube is positioned
3. Earth screen and armourFault-current path and touch voltage at the gland plateScreen bond and armour bond both made off and both reaching the panel earth barContinuity reading
4. Crimp the lug, mark the phaseCurrent path and phase identityDie matched to lug and conductor class, full closure, no strands cut, phase marked before bolting upDie number, crimp count per barrel
5. Fix the cores and hold spacingClearance and mechanical load on the lugSpacing to the panel drawing, bend radius respected, support bracket torquedTorque value
6. Test and hand overProof before energisationInsulation resistance, withstand test at the specified level, phase sequenceTest sheet and instrument printout

Stages 1 and 2: strip to the drawing, then cut the screen once

Stripping is measurement, not cutting. The kit drawing gives the lengths from the conductor end — insulation strip, screen cut-back, oversheath removal, and on three-core sets the length of core separation. Those lengths are written against a nominal cable. The cable on the drum is not nominal. Measure the insulation diameter at three points along the length to be stripped and compare it with the window the supplier publishes for the set in hand: adjacent set sizes are separated by a few millimetres, which is why a set chosen on cross-section alone is regularly one size out.

The screen cut decides the life of the termination. The semi-conductive layer has to be cut square without scoring the insulation beneath it, and the residue has to come off so the insulation surface is uniformly clean. What is left behind is a conductive film sitting exactly where the field is highest, and it does not announce itself at commissioning. It appears as tracking after a few years in service, when the repair is a new installation plus an unplanned outage.

Seat the stress-control element on the reference mark the kit provides, and photograph the cut before the tube is slid into position. That photograph is the only evidence that the work matched the drawing, and it costs the crew ten seconds. On a heat-shrink set the same evidence matters more, because the torch removes any chance of a second attempt.

Stages 3 and 4: earth first, then crimp and phase-mark

The earth connection to the metallic screen is made off before the insulating tube is positioned, not after. Once a cold-shrink tube has relaxed onto the cable it cannot be moved, so a fitter who reaches for the screen afterwards cuts the tube off and consumes the set. On armoured cable there are two separate connections — the screen bond and the armour bond — and both have to arrive at the earth bar of the panel rather than stop at the cable gland, where they carry nothing.

Crimping is a die problem before it is a technique problem. The die has to match the lug and the conductor class, copper or aluminium, and for aluminium the bimetallic transition. The crimp has to close fully, and the number of crimps along the barrel is set by the lug manufacturer rather than by how the tool feels. A partial closure looks acceptable and behaves as a resistance; the failure shows up as heat at full load, months later, inside a panel nobody opens on a schedule.

Finished low-voltage four-core cold-shrink termination with colour-coded phase tubes and copper ring lugs on every core

Phase identification belongs to the same stage. Colour-coded boots or markers go on before the lug is bolted to the busbar, because after that the access is gone and a phase identified with tape at handover is a phase that gets re-marked wrongly during a later outage. The photograph above is a finished low-voltage four-core set, and it shows the two features that carry over unchanged to medium voltage work: colour-coded phase tubes on every core, and a lug crimped on each one before anything is closed up.

Stages 5 and 6: hold the spacing, then test and hand over

Phase spacing is a dimension on the panel drawing, not a judgement about what looks even. Inside a cable compartment the termination has to preserve the phase-to-phase and phase-to-earth distances the switchgear was designed and type tested to, with the cores trained no tighter than the minimum bend radius the accessory supplier states. A core bent past that radius lifts the screen away from the insulation at the bend, and starts exactly the tracking the screen cut was meant to prevent.

Nothing is energised on a visual check. The sequence is insulation resistance from each core to earth and between cores, then a withstand test at the level the project specification calls for — on MV cable work that is normally a VLF withstand, with the voltage and duration taken from the specification rather than from the accessory supplier. What that test proves, and what it cannot prove, is set out in the VLF cable testing guide.

The handover pack closes the procedure: kit serial numbers, measured cable diameters, crimp die numbers, torque values, the test sheet and the photograph of the screen cut. An inspector who receives that pack does not have to re-open a termination to accept it, and a maintenance team that inherits the file knows what was installed without stripping the panel.

Matching the set to the cable: diameter before voltage class

A termination set is ordered against the cable, not against the system voltage alone. Two three-core 26/35 kV cables of the same nominal cross-section from different manufacturers can differ in diameter through strand shape, screen construction and oversheath thickness, and a set sized for the smaller one will not close onto the larger one. Nahu Group publishes the size split for its three-core 26/35 kV cold-shrink sets as follows, and the same logic applies to any supplier's range.

Set sizeCable cross-section (mm²)Diameter window published for the set (mm)Set weight (kg)
3.1#50–9586–948.46
3.2#120–18598–1058.48
3.3#240–400111–1248.59
3.4#500–630by cross-section only9.05
3.5#700by cross-section only9.20
3.6#800by cross-section only9.30

Note what the table does and does not settle. Up to 400 mm² the catalogue quotes a diameter window, so the set can be confirmed against a measurement taken on site before the order is released. Above that the set is defined by cross-section alone, and the diameter has to be confirmed with the supplier. The weight column is not decoration either: it decides how the carton is handled on a pole and what the freight line looks like on a multi-circuit order.

Cold-shrink three-core cable termination kit laid out with shedded tubes, copper lugs, earth braid, tapes and sealing consumables

Where the cable has to be unplugged — for testing, for a ring position fed from either side, or where live working is part of the operating regime — the answer is a separable connector rather than a termination. A screened elbow plugs onto a bushing and is held by a bracket, so the circuit can be broken without cutting anything. It is a different purchase from the kit shown above, ordered against the bushing and the cable rather than against a strip drawing.

Black 15 kV 200 A elbow separable connector with earth lead, metal mounting bracket and two fixing bolts

What changes between an 11 kV set and a 33 kV set

An 11 kV termination and a 33 kV termination are the same six stages with different numbers inside them. What changes with the voltage class is how much cable preparation the field control needs: a 33 kV cable carries a thicker extruded wall and a longer semi-conductive cut-back, so the stress-control element is longer, the strip dimension measured from the conductor end is greater, and core separation on a three-core set consumes more of the length left in the compartment.

The second difference that reaches procurement is outdoor creepage. A 33 kV outdoor set carries more sheds than an 11 kV set on the same route, and on a coastal or polluted site the shed count rather than the voltage class decides whether the set is acceptable. Neither figure is a catalogue constant across suppliers: both are read from the kit drawing for the set actually being installed.

Item11 kV position33 kV positionWhere the value is fixed
Cable class in use6.35/11 kV, or 8.7/15 kV where earth faults are not cleared quickly19/33 kV, or 26/35 kV on the sets described aboveCable data sheet
Extruded insulation wallThinner wallThicker wallCable data sheet, in mm
Semi-conductive cut-backShorterLongerKit installation drawing
Stress-control elementShorter elementLonger element, more wrap or a longer moulded coneKit installation drawing
Core separation, three-core setsConsumes less of the available lengthConsumes more, so the box position matters earlierKit installation drawing
Outdoor shedsFewerMoreKit drawing, against the specified pollution level
Screen bond and armour bondCross-section set by the projectCross-section set by the projectProject specification, not the accessory supplier
Withstand testVLF level set by the specificationVLF level set by the specificationProject specification

That table contains no millimetres on purpose. Strip length, cut-back and shed count are properties of one supplier's kit for one cable, and a number lifted from another supplier's drawing is how a set ends up half consumed on site. Ask for the drawing for the set being supplied, compare its cable window with a diameter measured on the drum, and the class difference looks after itself.

Eight non-conformities that fail inspection

The list below is what an inspector with a drawing and a torch finds, in roughly the order it is found. Each line names the visible evidence and the commercial consequence, because the consequence is what the buyer is paying to avoid.

Non-conformityWhat is visible at inspectionWhat it costs
Screen cut not square, or insulation scored under itA visible step, or a nick that shows as a white mark under the tubeTracking years later; set replaced and outage re-planned
Semi-conductive residue left above the cutDull grey film on an insulation surface that should be uniformly mattPartial discharge at commissioning; fails the withstand test
Stress-control element off its markReference line visible above or below the elementField concentration at the cut; puncture at the first impulse
Tube positioned before the earth tail was made offEarth tail emerging from under a closed tubeSet consumed; cable cut back
Lug crimped after the tube was installedCrushed tube, deformed sheds at the lug endSet consumed
Wrong die, or a crimp not fully closedLug loose on the conductor, heat discolouration at the barrelThermal fault at full load
Phase spacing not to the panel drawingCores trained tight, or phases closer than the drawing allowsFlashover on first energisation
No test record, or the test sheet without instrument outputHandover pack incompletePanel rejected at takeover; retest after energisation date slips

Only a few of these can be corrected without consuming a set. The rest end the shift: the cable is cut back, a replacement set is ordered against a lead time, and the energisation date moves. That is why the strip drawing and the kit content list are procurement documents. A crew working to a dimension does not consume kits, and a buyer who has priced a second mobilisation into the project is already paying for the risk.

What to write into the RFQ and the datasheet

An enquiry that produces comparable quotations separates the cable, the installation and the documentation. Anything left out comes back as an assumption, and the assumption is where the rework starts.

  • Cable designation U0/U, conductor material and cross-section, and the manufacturer's insulation diameter where it is known
  • Indoor or outdoor, and the pollution level the site is specified to
  • Termination or separable connector, stated as a requirement rather than left to the supplier
  • Panel or switchgear type, so phase spacing and the earth bar position can be checked against the set
  • Test requirements, the level, and who witnesses the test
  • Kit content list, installation drawing with strip dimensions, and the type test report for the accessory family to IEC 61442
  • Packing, and whether sets are quoted per phase or per three-phase circuit

The documentation line is the one most often dropped, and it is the one an inspector asks for first. A set without a strip drawing cannot be installed to a dimension; a set without a type test report covering the cable range being ordered cannot be accepted, whatever the hardware looks like on the bench. Ask for the report number and the cable range it covers, not for a certificate in general terms.

Where Nahu Group Fits

Nahu Group manufactures cable accessories alongside its current transformers, voltage transformers and switchgear: cold-shrink termination sets for 0.6/1 kV cable and for 26/35 kV three-core cable, intermediate joints and separable connectors. The full range is on the cable accessories product page, and the two sets used as examples above are the NLS-35 indoor three-core set and its outdoor counterpart; the low-voltage set in the photograph is the 0.6/1 kV cold-shrink.

To get a configuration, send the cable designation and cross-section, the measured or catalogue insulation diameter, whether the position is indoor or outdoor, the pollution level, the number of circuits, and the panel drawing where the termination lands inside switchgear. That is enough to come back with a set number, a strip drawing and a delivery date, without a second round of questions.

Frequently Asked Questions

How long does a medium voltage cable termination take to install?

Time is set by the cable and the access, not by the voltage class. A three-core 11 kV set inside a panel is roughly half a shift for a two-man crew, including the test; a 33 kV outdoor set with sheds takes longer, and a position with no working platform longer again. The kit drawing, not the quotation, is what a crew should be timed against.

Can a cold-shrink termination be repositioned once the tube has closed?

No. The tube closes under its own elastic memory and grips the cable along its whole length. Lifting it tears the stress-control geometry or leaves an air gap that tracking will find later. If the stress-control element is not on its mark, the tube comes off with a knife and a new set goes on.

What test proves the termination before energisation?

Insulation resistance first, then a withstand test at the level the project specification sets, which on medium voltage cable work is normally a VLF test. The withstand test finds gross defects such as a damaged tube or a misplaced stress cone. It does not find a termination with too little creepage, which will track in service whatever the test result.

Should the set be chosen by cable cross-section or by diameter?

Both, in that order. Cross-section places the set in a size band and the measured diameter confirms it. Cables of the same nominal cross-section from different manufacturers differ in diameter, and a set one size small will not close onto the cable. Above 400 mm² Nahu Group publishes the set by cross-section only, so the diameter is confirmed with the supplier.

Is the earth connection made before or after the tube is fitted?

Before. The screen bond and the armour bond are made off and routed to the panel earth bar while the screen is still accessible. Once the tube is in place the screen cannot be reached, and cutting the tube back to reach it destroys the set. Both bonds have to arrive at the earth bar, not stop at the gland plate.

What documents should ship with the kit?

An installation drawing with strip dimensions for the cable range the set covers, a kit content list, and a type test report for the accessory family to IEC 61442 with the report number and the cable range it covers. Ask for the drawing before the order, because a set without one cannot be installed to a dimension.

Sources and Further Reading

Published Nov 21, 2026 · Nahu Group (NAHU Electric Technology)