A 0.6/1 kV cable termination procedure is four steps — crimp the lug, restore the insulation, mark the phases, test insulation resistance — and the set is decided in the second one. The cold-shrink tube closes once; if it closes over a strip length that missed the drawing, or over a cable outside the set's diameter window, the work is repeated rather than corrected.
That is why the procedure belongs in the procurement pack, not only in the toolbox. The set is ordered against a measured cable, the lug against a measured conductor, the die against a marked lug, and the test against a number written before anyone opens a box.
What each of the four steps has to leave behind
Read the procedure as four gates. Each produces what the next one depends on, and each leaves a record a third party can check without having watched the work. On low voltage work the records are short, which is exactly why they get skipped.
| Step | What it produces | Check before the next gate opens | Record left behind |
|---|---|---|---|
| 1. Crimp the lug | A current path from conductor strands into the lug barrel | Die matched to lug and conductor class, full die closure, no strands sheared, barrel length right for the lug and stud | Die code and crimp count per barrel |
| 2. Restore insulation | A sealed, fully insulated termination up to the palm | Tube seated on its reference mark, no air path under the shed, cores separated to the drawing before the breakout is pulled | Photograph of the seated tube, kit serial |
| 3. Mark phases | Phase identity that survives twenty years of maintenance | Each core marked at both ends before bolting, scheme agreeing with panel drawing and cable schedule | Marking scheme as issued for approval |
| 4. Test insulation | Proof that the work is fit to energise | Instrument on the correct range, cores separated, reading held for the full duration | Reading, instrument serial, ambient temperature |
Strip lengths come from the kit drawing, not from habit
Every cold-shrink set ships with an installation drawing that fixes four dimensions: conductor standing proud of the insulation, insulation cut-back, oversheath removal, and on multicore cable the core separation before the breakout seats. Those numbers are drawn for the cable range the set covers, and they change with core count. A three-core drawing is not a five-core drawing with two cores removed.
The five-core arrangement above shows why. Five tubes, a five-finger breakout and five phase tapes are supplied as one set, and the breakout only pulls down once the cores sit at the separation on the drawing. Spread them short and the fingers fold; spread them long and the oversheath that should sit under the breakout has gone. Neither fault shows at the resistance test.
So the drawing is a purchasing document. Ask for it against the cable range in the enquiry and keep the version matching the kit serial delivered; without it the crew strips to habit, and the habit is whatever the last site used.
Size the set on measured diameter, not on cross-section
Cross-section tells you the conductor, not the outside diameter of the insulation — which is what the tube grips, and which varies with compound and cable maker. Two 4 × 95 mm² cables from different works can sit a millimetre or two apart, and adjacent set sizes are separated by only a few. Measure at three points along the length to be stripped, average, and order against the window.
| Cores | Set | Model | Conductor range (mm²) | Main insulation OD window (mm) | Set weight (kg) |
|---|---|---|---|---|---|
| Four | 4.0# | TLS1-4x0 | 10–16 | 17.6–20.2 | 0.85 |
| Four | 4.1# | TLS1-4x1 | 25–50 | 24.3–25.8 | 0.87 |
| Four | 4.2# | TLS1-4x2 | 70–120 | 29.8–36.9 | 1.03 |
| Four | 4.3# | TLS1-4x3 | 150–240 | 41.0–50.8 | 1.07 |
| Four | 4.4# | TLS1-4x4 | 300–400 | 56.2–58.0 | 1.47 |
| Four | 4.5# | TLS1-4x5 | 500–630 | 60.0–62.0 | 1.72 |
| Five | 5.0# | TLS1-5x0 | 10–16 | 18.5–21.2 | 0.84 |
| Five | 5.1# | TLS1-5x1 | 25–50 | 25.6–32.7 | 0.84 |
| Five | 5.2# | TLS1-5x2 | 70–120 | 38.1–47.3 | 1.09 |
| Five | 5.3# | TLS1-5x3 | 150–240 | 53.2–55.0 | 1.19 |
| Five | 5.4# | TLS1-5x4 | 300–400 | 61.0–64.0 | 1.45 |
| Five | 5.5# | TLS1-5x5 | 500–630 | 73.0–75.0 | 1.48 |
A five-core set is not a four-core set plus one tube. The same 70–120 mm² conductor needs the 5.2# set, whose window starts at 38.1 mm, against 29.8 mm for the four-core version, because five insulated cores bundle into a larger circle. The full ranges sit on the four-core 0.6/1 kV terminal set and five-core 0.6/1 kV terminal set pages.
Crimping: die, full closure, and the torque you record
The die is chosen from the lug, not the cable. Lug catalogues print a die code against each barrel size and conductor class, and the head must reach full closure — hydraulic tools signal it by pressure relief or a mechanical stop. A crimp stopped just short looks closed, holds a hand pull, and fails a thermal survey at full load.
| Fastener | What sets the value | Commonly specified range | What goes on the test sheet |
|---|---|---|---|
| M8 lug-to-busbar stud | Lug and panel hardware data sheet, stud grade, washer type | Around 20–25 N·m for class 8.8 hardware, dry | Figure used and torque wrench serial |
| M10 lug-to-busbar stud | Same, plus busbar thickness behind the joint | Around 40–50 N·m for class 8.8 hardware, dry | Figure used, and a re-torque check after 24 hours on vibrating plant |
| Cable gland and earth tag | Gland maker, and the panel earth continuity requirement | Per gland data sheet; continuity measured, not assumed | Continuity reading in milliohms |
| Crimp die | Lug catalogue code for barrel size and conductor class | Full die closure, one crimp per size step | Die code and crimp count per barrel |
Two details cost the most rework: strands sheared at the barrel mouth, which cut the current path exactly where bending stress sits, and a barrel too long for the lug body, which leaves a void no tape fills. On aluminium, brush the oxide off under neutral compound and crimp at once; it reforms within minutes in humid air.
Treat the torque column above as a starting point to confirm, not a specification. Where the lug maker and the panel standard disagree, the tighter figure usually governs and the difference is settled in writing before the joint is made. A joint with no recorded torque is an open item at handover however good it looks.
Restoring the insulation, then marking the phases
Cold-shrink restoration is mechanical: the tube is factory-expanded over a removable core, the core unwinds from the inside, and the tube contracts onto the cable. No heat source near the insulation, no dependence on flame technique — which is why the method displaced tape and heat-shrink in confined, partly energised switchrooms. The order still matters: breakout first, tubes second, everything seated before the core is pulled.
The two-core set above is the smallest arrangement in the family and the clearest place to see the logic. Halve the core count and you halve the tubes, but the sealing step does not halve: the breakout still has to close over clean oversheath, with tape lapped in the direction the drawing shows.
Phase marking is documentation as much as workmanship. Mark each core at both ends, to the cable schedule, before the cores are bent into the terminals; after bolting the only readable surface is the top of the palm. Brown, black and grey for L1 to L3 with blue neutral and green-yellow earth is the common IEC-based convention, and a project specifying another scheme wins. What matters is that the scheme is written down and matches both ends.
Copper-to-aluminium transition lugs: four criteria
Aluminium conductors are common on incoming LV feeders and rare on panel wiring, so the transition lands at the terminal. A plain copper lug compressed onto aluminium is not a transition; it is a galvanic cell under load. Four criteria decide the part.
- Bimetallic construction. Palm and barrel joined by friction or explosion welding, so the interface is metallurgical rather than a coating. A plated aluminium lug solves one metal only; it does not solve a copper-to-aluminium joint.
- Conductor class. Stranded, flexible and sector-shaped aluminium need different barrel geometries. A lug drawn for round stranded core will not close on a shaped one without leaving a void.
- Test class. State the connector class required against IEC 61238-1 and ask for the type test report covering the conductor range ordered, not the family in general.
- Creep allowance. Aluminium relaxes under compression. Specify a re-torque interval for the first year, or a Belleville washer stack, and write it into the maintenance schedule.
The commercial version is simple: a bimetallic lug costs a fraction of the labour to replace one that corroded, and the failure surfaces as a hot joint on an infrared survey long after the installer left site.
What the insulation resistance test has to prove
The last gate is a direct-current insulation resistance measurement, core to earth and core to core, far end isolated, after the termination is complete and before the circuit is energised. For 400/230 V the usual acceptance level is 1 MΩ at 500 V DC held for a minute; projects with wet routes or long runs often write a higher figure, and the specification wins. Record the reading, the ambient temperature and the instrument serial.
| Test | Setting | Typical acceptance | Why it is not optional |
|---|---|---|---|
| Insulation resistance, core to earth | 500 V DC, one minute | 1 MΩ minimum for 400/230 V circuits, higher where specified | Detects a damaged tube or a core touching the breakout |
| Insulation resistance, core to core | 500 V DC, one minute | Same level as core to earth | Detects cross-phase damage hidden under the breakout |
| Protective conductor continuity | Low-resistance ohmmeter | Around 1 Ω for the run, per the project method statement | Proves the earth path through gland and tag |
| Phase sequence | Phase rotation meter at the remote end | Matches the cable schedule | Prevents reverse rotation on first start |
A pass here is not proof of workmanship. A tube seated on the wrong mark reads several hundred megohms on a dry day and fails after a wet season. The test proves the insulation is intact at the moment of measurement; the drawing and the photograph prove it was built to a dimension. Both belong in the handover pack.
Five mistakes and what each one costs
Each of these reaches inspection repeatedly, and each has a price that can be stated before the order is placed.
| Mistake | What it looks like on site | Commercial cost |
|---|---|---|
| Set chosen on cross-section alone | Tube will not seal, or seals slack on the insulation | Second set plus a second visit; the first set is scrap |
| Cores spread to the wrong separation | Breakout fingers fold or ride up the oversheath | Whole termination remade; the breakout cannot be reused |
| Crimp die not fully closed | Lug warm at full load, discoloured after months | Re-termination plus a thermal survey of every joint on the board |
| Phase marking after bolting | Marks on the palm only, unreadable in service | Continuity testing to identify phases at the next shutdown |
| Plain copper lug on aluminium | White corrosion at the barrel, rising resistance | Bimetallic replacement and a re-torque regime for the feeder |
Every one of these is decided before material arrives, by what the enquiry said. None is decided by the fitter's skill, and none is caught by the resistance test on the day. State the measured diameter, the core count, the conductor material and the test level, and four of the five disappear.
What to write into the RFQ and the datasheet
Write the requirement list as data. A termination set is bought against dimensions, not a description, and the items below let a supplier quote one correct part instead of a range.
- Cable construction to IEC 60502-1: core count, nominal cross-section, conductor material and class, and measured main insulation diameter in millimetres
- Voltage class 0.6/1 kV, indoor panel entry or outdoor, with pollution level where it applies
- Lug type, stud size and material, plus the die code the crimping tool carries
- Installation drawing with the four strip dimensions, kit content list and conformity certificate
- Test requirements: insulation resistance level, continuity method, phase sequence, and who witnesses
- Quantity in sets per circuit, packing, and whether spare tubes are wanted for the maintenance store
Two items do most of the work: the measured diameter removes the sizing error, the drawing request removes the strip-length error. The rest is administration that only becomes expensive when missing. A three-core 0.6/1 kV terminal or two-core 0.6/1 kV terminal ships with phase tapes, sealing tape, cleaning papers, gloves, an installation booklet and a certificate of conformity, so the list mainly confirms the same applies to the size ordered.
On the medium voltage side of the same panel, the sequence changes more than the principle does; the six-stage medium voltage termination procedure sets out where the screen is cut and why that step cannot be recovered. For construction choices, see the five termination constructions compared and the cold shrink versus heat shrink selection.
Where Nahu Group Fits
Nahu Group manufactures cold-shrink cable accessories for 0.6/1 kV and medium voltage cable, including fully cold-shrink terminal sets for two, three, four and five core low voltage cable. The cable accessories range page lists conductor ranges and insulation diameter windows for each set size. Send the cable construction, the measured insulation diameter, the core count and the quantity in sets, and the reply will be a specific set size with its installation drawing and a test schedule for the submittal.
Frequently Asked Questions
How long does a 0.6/1 kV termination take to install?
A four or five core cold-shrink termination with crimped lugs typically takes thirty to sixty minutes for two people once the cable is prepared and the panel accessible. Crimping and breakout seating take most of it.
Can heat-shrink be used instead of cold-shrink at 0.6/1 kV?
Yes, heat-shrink is still widely used at low voltage and some utilities specify it. It depends on flame technique and a permitted heat source in the panel, and it cannot be reworked once shrunk. Cold-shrink needs neither.
Why does the set size not follow the cable cross-section?
The tube seals on the outside diameter of the main insulation, and that diameter depends on the compound, the conductor shape and the cable maker. Two cables of the same cross-section can differ by a millimetre or two, which is the order of the gap between adjacent set sizes.
What insulation resistance should a new LV termination show?
For a 400/230 V circuit the usual acceptance level is 1 MΩ measured at 500 V DC for one minute, core to earth and core to core. A healthy new termination normally reads far higher, and a project specification may set a higher minimum.
Can a copper lug be used directly on an aluminium conductor?
Not directly. The joint forms a galvanic couple, and with moisture present the aluminium corrodes at the contact face, resistance rises and the joint runs hot. Use a bimetallic lug with a welded palm-to-barrel interface, prepare the conductor under neutral compound, and plan a re-torque check for the first year.
Do the terminal sets include lugs?
The cold-shrink terminal sets are insulation restoration kits: tubes, breakout, phase tapes, sealing tape, cleaning materials, gloves, installation booklet and a certificate of conformity. Lugs are ordered separately against conductor material, stud size and crimping tool.
Sources and Further Reading
- IEC 60364-5-52 — Low-voltage electrical installations, Part 5-52: Selection and erection of electrical equipment, wiring systems — conductor sizing, installation methods and the correction factors that decide whether the terminated cable is adequate in the first place
- IEC 60502-1 — Power cables with extruded insulation for rated voltages up to and including 1 kV: the cable construction and insulation dimensions the set has to fit
- IEC 61238-1 — Compression and mechanical connectors for power cables: the connector test classes to quote in the enquiry for lugs and bimetallic transitions
Published Nov 22, 2026 · Nahu Group (NAHU Electric Technology)