A 0.6/1 kV cable termination procedure is four steps — crimp the lug, restore the insulation, mark the phases, test insulation resistance — and the set is decided in the second one. The cold-shrink tube closes once; if it closes over a strip length that missed the drawing, or over a cable outside the set's diameter window, the work is repeated rather than corrected.

0.6/1 kV fully cold shrink three-core cable termination set with three grey tubes, three-finger breakout and phase tapes

That is why the procedure belongs in the procurement pack, not only in the toolbox. The set is ordered against a measured cable, the lug against a measured conductor, the die against a marked lug, and the test against a number written before anyone opens a box.

What each of the four steps has to leave behind

Read the procedure as four gates. Each produces what the next one depends on, and each leaves a record a third party can check without having watched the work. On low voltage work the records are short, which is exactly why they get skipped.

StepWhat it producesCheck before the next gate opensRecord left behind
1. Crimp the lugA current path from conductor strands into the lug barrelDie matched to lug and conductor class, full die closure, no strands sheared, barrel length right for the lug and studDie code and crimp count per barrel
2. Restore insulationA sealed, fully insulated termination up to the palmTube seated on its reference mark, no air path under the shed, cores separated to the drawing before the breakout is pulledPhotograph of the seated tube, kit serial
3. Mark phasesPhase identity that survives twenty years of maintenanceEach core marked at both ends before bolting, scheme agreeing with panel drawing and cable scheduleMarking scheme as issued for approval
4. Test insulationProof that the work is fit to energiseInstrument on the correct range, cores separated, reading held for the full durationReading, instrument serial, ambient temperature

Strip lengths come from the kit drawing, not from habit

Every cold-shrink set ships with an installation drawing that fixes four dimensions: conductor standing proud of the insulation, insulation cut-back, oversheath removal, and on multicore cable the core separation before the breakout seats. Those numbers are drawn for the cable range the set covers, and they change with core count. A three-core drawing is not a five-core drawing with two cores removed.

0.6/1 kV fully cold shrink five-core cable termination set laid out with five tubes and five phase tapes

The five-core arrangement above shows why. Five tubes, a five-finger breakout and five phase tapes are supplied as one set, and the breakout only pulls down once the cores sit at the separation on the drawing. Spread them short and the fingers fold; spread them long and the oversheath that should sit under the breakout has gone. Neither fault shows at the resistance test.

So the drawing is a purchasing document. Ask for it against the cable range in the enquiry and keep the version matching the kit serial delivered; without it the crew strips to habit, and the habit is whatever the last site used.

Size the set on measured diameter, not on cross-section

Cross-section tells you the conductor, not the outside diameter of the insulation — which is what the tube grips, and which varies with compound and cable maker. Two 4 × 95 mm² cables from different works can sit a millimetre or two apart, and adjacent set sizes are separated by only a few. Measure at three points along the length to be stripped, average, and order against the window.

CoresSetModelConductor range (mm²)Main insulation OD window (mm)Set weight (kg)
Four4.0#TLS1-4x010–1617.6–20.20.85
Four4.1#TLS1-4x125–5024.3–25.80.87
Four4.2#TLS1-4x270–12029.8–36.91.03
Four4.3#TLS1-4x3150–24041.0–50.81.07
Four4.4#TLS1-4x4300–40056.2–58.01.47
Four4.5#TLS1-4x5500–63060.0–62.01.72
Five5.0#TLS1-5x010–1618.5–21.20.84
Five5.1#TLS1-5x125–5025.6–32.70.84
Five5.2#TLS1-5x270–12038.1–47.31.09
Five5.3#TLS1-5x3150–24053.2–55.01.19
Five5.4#TLS1-5x4300–40061.0–64.01.45
Five5.5#TLS1-5x5500–63073.0–75.01.48

A five-core set is not a four-core set plus one tube. The same 70–120 mm² conductor needs the 5.2# set, whose window starts at 38.1 mm, against 29.8 mm for the four-core version, because five insulated cores bundle into a larger circle. The full ranges sit on the four-core 0.6/1 kV terminal set and five-core 0.6/1 kV terminal set pages.

Crimping: die, full closure, and the torque you record

The die is chosen from the lug, not the cable. Lug catalogues print a die code against each barrel size and conductor class, and the head must reach full closure — hydraulic tools signal it by pressure relief or a mechanical stop. A crimp stopped just short looks closed, holds a hand pull, and fails a thermal survey at full load.

FastenerWhat sets the valueCommonly specified rangeWhat goes on the test sheet
M8 lug-to-busbar studLug and panel hardware data sheet, stud grade, washer typeAround 20–25 N·m for class 8.8 hardware, dryFigure used and torque wrench serial
M10 lug-to-busbar studSame, plus busbar thickness behind the jointAround 40–50 N·m for class 8.8 hardware, dryFigure used, and a re-torque check after 24 hours on vibrating plant
Cable gland and earth tagGland maker, and the panel earth continuity requirementPer gland data sheet; continuity measured, not assumedContinuity reading in milliohms
Crimp dieLug catalogue code for barrel size and conductor classFull die closure, one crimp per size stepDie code and crimp count per barrel

Two details cost the most rework: strands sheared at the barrel mouth, which cut the current path exactly where bending stress sits, and a barrel too long for the lug body, which leaves a void no tape fills. On aluminium, brush the oxide off under neutral compound and crimp at once; it reforms within minutes in humid air.

Treat the torque column above as a starting point to confirm, not a specification. Where the lug maker and the panel standard disagree, the tighter figure usually governs and the difference is settled in writing before the joint is made. A joint with no recorded torque is an open item at handover however good it looks.

Restoring the insulation, then marking the phases

Cold-shrink restoration is mechanical: the tube is factory-expanded over a removable core, the core unwinds from the inside, and the tube contracts onto the cable. No heat source near the insulation, no dependence on flame technique — which is why the method displaced tape and heat-shrink in confined, partly energised switchrooms. The order still matters: breakout first, tubes second, everything seated before the core is pulled.

Fully cold shrink two-core cable termination set with two grey tubes, two-finger breakout and sealing tape

The two-core set above is the smallest arrangement in the family and the clearest place to see the logic. Halve the core count and you halve the tubes, but the sealing step does not halve: the breakout still has to close over clean oversheath, with tape lapped in the direction the drawing shows.

Phase marking is documentation as much as workmanship. Mark each core at both ends, to the cable schedule, before the cores are bent into the terminals; after bolting the only readable surface is the top of the palm. Brown, black and grey for L1 to L3 with blue neutral and green-yellow earth is the common IEC-based convention, and a project specifying another scheme wins. What matters is that the scheme is written down and matches both ends.

Copper-to-aluminium transition lugs: four criteria

Aluminium conductors are common on incoming LV feeders and rare on panel wiring, so the transition lands at the terminal. A plain copper lug compressed onto aluminium is not a transition; it is a galvanic cell under load. Four criteria decide the part.

  • Bimetallic construction. Palm and barrel joined by friction or explosion welding, so the interface is metallurgical rather than a coating. A plated aluminium lug solves one metal only; it does not solve a copper-to-aluminium joint.
  • Conductor class. Stranded, flexible and sector-shaped aluminium need different barrel geometries. A lug drawn for round stranded core will not close on a shaped one without leaving a void.
  • Test class. State the connector class required against IEC 61238-1 and ask for the type test report covering the conductor range ordered, not the family in general.
  • Creep allowance. Aluminium relaxes under compression. Specify a re-torque interval for the first year, or a Belleville washer stack, and write it into the maintenance schedule.

The commercial version is simple: a bimetallic lug costs a fraction of the labour to replace one that corroded, and the failure surfaces as a hot joint on an infrared survey long after the installer left site.

What the insulation resistance test has to prove

The last gate is a direct-current insulation resistance measurement, core to earth and core to core, far end isolated, after the termination is complete and before the circuit is energised. For 400/230 V the usual acceptance level is 1 MΩ at 500 V DC held for a minute; projects with wet routes or long runs often write a higher figure, and the specification wins. Record the reading, the ambient temperature and the instrument serial.

TestSettingTypical acceptanceWhy it is not optional
Insulation resistance, core to earth500 V DC, one minute1 MΩ minimum for 400/230 V circuits, higher where specifiedDetects a damaged tube or a core touching the breakout
Insulation resistance, core to core500 V DC, one minuteSame level as core to earthDetects cross-phase damage hidden under the breakout
Protective conductor continuityLow-resistance ohmmeterAround 1 Ω for the run, per the project method statementProves the earth path through gland and tag
Phase sequencePhase rotation meter at the remote endMatches the cable schedulePrevents reverse rotation on first start

A pass here is not proof of workmanship. A tube seated on the wrong mark reads several hundred megohms on a dry day and fails after a wet season. The test proves the insulation is intact at the moment of measurement; the drawing and the photograph prove it was built to a dimension. Both belong in the handover pack.

Five mistakes and what each one costs

Each of these reaches inspection repeatedly, and each has a price that can be stated before the order is placed.

MistakeWhat it looks like on siteCommercial cost
Set chosen on cross-section aloneTube will not seal, or seals slack on the insulationSecond set plus a second visit; the first set is scrap
Cores spread to the wrong separationBreakout fingers fold or ride up the oversheathWhole termination remade; the breakout cannot be reused
Crimp die not fully closedLug warm at full load, discoloured after monthsRe-termination plus a thermal survey of every joint on the board
Phase marking after boltingMarks on the palm only, unreadable in serviceContinuity testing to identify phases at the next shutdown
Plain copper lug on aluminiumWhite corrosion at the barrel, rising resistanceBimetallic replacement and a re-torque regime for the feeder

Every one of these is decided before material arrives, by what the enquiry said. None is decided by the fitter's skill, and none is caught by the resistance test on the day. State the measured diameter, the core count, the conductor material and the test level, and four of the five disappear.

What to write into the RFQ and the datasheet

Write the requirement list as data. A termination set is bought against dimensions, not a description, and the items below let a supplier quote one correct part instead of a range.

  • Cable construction to IEC 60502-1: core count, nominal cross-section, conductor material and class, and measured main insulation diameter in millimetres
  • Voltage class 0.6/1 kV, indoor panel entry or outdoor, with pollution level where it applies
  • Lug type, stud size and material, plus the die code the crimping tool carries
  • Installation drawing with the four strip dimensions, kit content list and conformity certificate
  • Test requirements: insulation resistance level, continuity method, phase sequence, and who witnesses
  • Quantity in sets per circuit, packing, and whether spare tubes are wanted for the maintenance store

Two items do most of the work: the measured diameter removes the sizing error, the drawing request removes the strip-length error. The rest is administration that only becomes expensive when missing. A three-core 0.6/1 kV terminal or two-core 0.6/1 kV terminal ships with phase tapes, sealing tape, cleaning papers, gloves, an installation booklet and a certificate of conformity, so the list mainly confirms the same applies to the size ordered.

On the medium voltage side of the same panel, the sequence changes more than the principle does; the six-stage medium voltage termination procedure sets out where the screen is cut and why that step cannot be recovered. For construction choices, see the five termination constructions compared and the cold shrink versus heat shrink selection.

Where Nahu Group Fits

Nahu Group manufactures cold-shrink cable accessories for 0.6/1 kV and medium voltage cable, including fully cold-shrink terminal sets for two, three, four and five core low voltage cable. The cable accessories range page lists conductor ranges and insulation diameter windows for each set size. Send the cable construction, the measured insulation diameter, the core count and the quantity in sets, and the reply will be a specific set size with its installation drawing and a test schedule for the submittal.

Frequently Asked Questions

How long does a 0.6/1 kV termination take to install?

A four or five core cold-shrink termination with crimped lugs typically takes thirty to sixty minutes for two people once the cable is prepared and the panel accessible. Crimping and breakout seating take most of it.

Can heat-shrink be used instead of cold-shrink at 0.6/1 kV?

Yes, heat-shrink is still widely used at low voltage and some utilities specify it. It depends on flame technique and a permitted heat source in the panel, and it cannot be reworked once shrunk. Cold-shrink needs neither.

Why does the set size not follow the cable cross-section?

The tube seals on the outside diameter of the main insulation, and that diameter depends on the compound, the conductor shape and the cable maker. Two cables of the same cross-section can differ by a millimetre or two, which is the order of the gap between adjacent set sizes.

What insulation resistance should a new LV termination show?

For a 400/230 V circuit the usual acceptance level is 1 MΩ measured at 500 V DC for one minute, core to earth and core to core. A healthy new termination normally reads far higher, and a project specification may set a higher minimum.

Can a copper lug be used directly on an aluminium conductor?

Not directly. The joint forms a galvanic couple, and with moisture present the aluminium corrodes at the contact face, resistance rises and the joint runs hot. Use a bimetallic lug with a welded palm-to-barrel interface, prepare the conductor under neutral compound, and plan a re-torque check for the first year.

Do the terminal sets include lugs?

The cold-shrink terminal sets are insulation restoration kits: tubes, breakout, phase tapes, sealing tape, cleaning materials, gloves, installation booklet and a certificate of conformity. Lugs are ordered separately against conductor material, stud size and crimping tool.