A current transformer symbol is a drawing convention, not a specification: it shows where a CT sits on the circuit and how its windings relate to the primary, and never states the ratio, the class or the burden. The two marks that decide whether it can be wired correctly are the secondary winding and the polarity reference; leave either out and the reader guesses at what only a commissioning test can settle.

Through-type current transformer in black and red cast resin with a central primary window for cable or busbar

A single-line diagram, a three-line diagram and a protection schematic each reduce the same device to a different minimum, and the reader of one is rarely the reader of the other. When the symbol is thinner than its job, the gap gets closed by email after the panel is built.

What must a current transformer symbol show?

At minimum, four things: that a current-measuring device exists at that point, which winding arrangement it has, where the polarity reference sits, and where the secondary goes and at which single point it is earthed. Ratio, class, burden and instrument security factor belong in the schedule and on the nameplate; annotation beside a symbol does not turn those into a specification.

Both the IEC 60617 symbol set and IEEE/ANSI practice reduce the CT to a handful of shapes, and no shape is wrong in itself. What differs between drawing sets is how much of the secondary they show and how the terminals are designated. A sheet that borrows the single-line shape into a schematic is not simplified; it is missing information somebody must supply later.

The three ways a CT is drawn, and what each one is for

The three conventions are not interchangeable. On the single-line diagram the CT is a circle threaded by the feeder conductor. On the three-line diagram each phase is drawn separately, so the CT appears once per phase. On the schematic it becomes coupled windings with terminal designations, because that is the drawing the protection engineer wires from.

Drawing typeHow the CT appearsWhat it settles for the readerWhat it leaves to the schedule
Single-line diagramOne circle, or two, on the feeder conductor; sometimes a bar drawn through itThat current is measured here, and on which side of the breakerRatio, class, cores, burden, earthing
Three-line diagramOne CT per phase, each on its own conductor, cores sometimes drawn separatelyPhase allocation, and whether the set is three-phase or single-phaseTerminal designations, polarity reference, secondary wiring
Schematic / connection diagramPrimary as one turn or a bar; one or more secondaries labelled S1, S2Polarity, core assignment, where each core terminates and is earthedConstruction, dimensions, test values
Wiring and terminal diagramTerminal block references, multicore numbers, test linksWhich wire lands where, and where the shorting facility sitsEverything electrical; it assumes the schematic is right

A useful check when a set arrives is to read the CT in all three places and confirm that core count and polarity direction agree. Where the single-line shows one circle and the schematic two secondaries, the schedule is the tie-breaker, and the gap is a clarification request rather than something to settle on site with a meter.

The circle on the conductor: what a single-line CT symbol fixes

On the single-line diagram the CT is positional information. It says that measurement or protection current is taken at that point, and its position relative to the breaker and the voltage transformer says what the device can and cannot see. A CT on the busbar side of a breaker measures fault current the breaker does not clear; the same circle one line lower measures the feeder, and that changes the ratio, the class and the core count.

What the single-line cannot carry is the part that gets ordered: cores, ratio, class, burden, short-time withstand, earthing point. Values written beside the symbol are a convenience, not a specification, and ratios traced from an annotation to a purchase order diverge at the second revision.

This is also where the device family has to be named rather than implied. The current transformer is organised by mounting and voltage level — indoor cast-resin, outdoor, bushing and window types — properties the symbol never expresses. For the shapes beside the CT on the same sheet, the guide to switchgear symbols on a single-line drawing covers the breaker, disconnector and earthing switch.

Two circles with S1 and S2: reading the schematic symbol

In a schematic the CT becomes coupled windings: one primary turn, often a bar through the core, and one or more secondary windings labelled at their terminals. S1 and S2 are the secondary terminals of one core, P1 and P2 the primary terminals, and the polarity dot — or the convention that P1 and S1 are the same end — tells the reader which way secondary current flows. Remove the dot and the drawing no longer says whether the unit is additive or subtractive.

Red bushing-type current transformer with P1 polarity marking and 100/5 ratio marked on the body, on a steel bracket

The same information is cast into the hardware. On a bushing-type unit the P1 marking sits at one side of the through-hole and the ratio is printed on the body — a 100/5 unit carries that number and its P1 mark on the casting. A symbol that puts P1 on the cable side against a unit marked on the busbar side is an inspection finding.

Multi-core units are where schematic discipline pays. A unit with one metering core and two protection cores is drawn as three secondaries, designated 1S1/1S2, 2S1/2S2, each keeping its class and burden. Collapse them into one winding labelled S1/S2 and the cores become indistinguishable on paper; the metering circuit can end up on a 5P core while a relay is fed from a 0.5 class core.

What a missing secondary, dot or earth point costs

Five omissions account for most of the clarification traffic on CT drawings, and each one has a predictable place where it surfaces.

Left off the drawingWhat the reader has to assumeWhere the assumption surfaces
Secondary winding or core countThat one circle means a single-core unitAt order review, when a dual-core unit is needed for metering and protection
Polarity dot or P1/S1 conventionAdditive polarity, connected the conventional wayAt commissioning, when a directional or differential element misoperates
S1/S2 terminal designationsThat core one is metering and core two is protectionAt the test block, after the multicore is glanded and terminated
Earth point on the secondaryThat the panel builder will earth it at the nearest terminalAt inspection, as a second earth point or as no earth at all
Star or delta secondary connectionStar, with a neutral brought outWhen residual current is expected and no residual path exists

The commercial consequence is rarely one dramatic failure; it is one of four ordinary ones, each with a schedule attached:

  • Rework at the panel: a second core or a different ratio discovered after mounting means re-terminating or replacing a device inside a compartment never sized for it.
  • Rejected inspection: a nameplate that disagrees with the drawing, or an unmarked polarity terminal, is a documented non-conformity even when the hardware is correct.
  • Delayed energisation: a polarity or core-assignment fault found during commissioning pushes the feeder back by the re-test time, usually on the critical path.
  • Spare-part mismatch: a spare ordered against an ambiguous symbol arrives with the wrong core count and cannot replace the unit it was bought for.

A missing dot is settled at commissioning with a battery and a meter on a panel adjacent to live equipment; a missing core number is settled at the test block after the cable is made off. The procedure for checking CT polarity and secondary connections sets out the test and the protection functions that misoperate on a reversed core.

From the symbol to the unit that arrives in the crate

A drawing earns its keep only if the reader can map it onto the object on the bench. Three constructions cover the distribution range: the through type, where the primary conductor passes through a window in the casting; the bar-primary type, where a flat bar is cast into the body; and the wound-primary type, brought out to two terminals. They look different in the hand and are drawn identically on a single-line diagram.

Red cast-resin current transformer with two shedded primary bushings and terminal studs at the top for indoor mounting

On a two-bushing cast-resin unit the primary terminals are the studs at the top of the sheds and the secondary block sits under a cover in the base, beside the earthing terminal. Four checks cover most of what goes wrong between drawing and delivery: the P1 marking sits on the side the drawing specifies, the block is labelled per core, the ratio and class match the schedule, and the earth terminal is present.

What to write into the RFQ and the CT schedule

The symbol is not orderable; the schedule is. An RFQ that attaches a single-line diagram and one line of text is priced against the supplier's assumptions, and those are always the cheapest ones available — one core instead of three, a standard class instead of the specified one.

Schedule itemWhat to stateWhy the drawing cannot carry it
Rated primary and secondary currentRatio per core, for example 100/5 A or 200/1 A, and whether it is tappedThe symbol shows a device, not a ratio
Number of coresMetering, protection or both, and how many of eachOne circle looks the same for one core or four
Accuracy class and burdenClass per core, with burden in VA at the specified power factorClass is a nameplate and test value, not a shape
Protection parametersAccuracy limit factor for P cores, instrument security factor for metering coresNeither appears in any symbol convention
Polarity and connectionP1 orientation as installed, star or delta secondary, residual winding if requiredOnly the schematic can express it, and it must match the physical marking
System and insulationRated voltage, highest system voltage, impulse withstand, indoor or outdoor, ambientMounting and environment are outside the drawing's scope
DocumentsType test report, routine test record, outline drawing for approval, marking detailsCommercial deliverables, not drawing content

On documents, be specific. For inductive current transformers the governing standard is IEC 61869-2:2012, with general requirements in IEC 61869-1. Ask the supplier for the type test report covering the construction offered, the routine test record for the units shipped, and an outline drawing with terminal and polarity markings — then check that the drawing you approve matches the schematic.

Where Nahu Group Fits

Nahu Group manufactures indoor cast-resin and outdoor current transformers for medium-voltage distribution, in through, window and wound-primary constructions, with metering and protection cores set by the project schedule. The types referred to above are catalogue models in the current transformer — the LZZBJ9-10 indoor unit for panel mounting and the LZZW-10 outdoor unit for pole installations. To get a configuration, send the single-line diagram with the CT position marked, the schedule with ratio and class per core, the panel arrangement, and the quantity. If your polarity marks and the nameplate of the unit in store disagree, say so — that detail decides whether a replacement drops in or needs a new multicore. The voltage transformer symbol conventions are worth reading alongside this, since both devices share the same sheet.

Frequently Asked Questions

Does the current transformer symbol show the ratio?

No. The symbol shows that a device exists at that point and how its windings relate to the primary. The ratio belongs in the device schedule and on the nameplate. A ratio written beside a symbol is a reading aid; it becomes an instruction only when the same value appears in the schedule forming part of the contract.

Why is the CT one circle on a single-line diagram and two on a schematic?

The two drawings answer different questions. The single-line diagram shows that current is measured at a position on the circuit, so one circle is enough. The schematic has to be wired from, so it shows the primary and each secondary separately, with terminal designations and a polarity reference the installer can follow terminal by terminal.

What does the dot on a CT symbol actually mean?

It marks terminals instantaneously at the same polarity. With the dot at P1 and S1, current entering P1 produces secondary current leaving S1 in the conventional direction. Without the dot the reader falls back on the standard convention, and on a unit supplied with reversed polarity that assumption is wrong in a way only a commissioning test finds.

How are multiple cores shown on a drawing?

As separate secondary windings, each with its own terminal pair and a core prefix: 1S1/1S2 for the first core, 2S1/2S2 for the second. Each carries its own class and burden, so the numbering has to survive into the wiring schedule and the terminal block, or the cores become interchangeable on paper and are treated that way on site.

Can a CT symbol be left without an earth point on the secondary?

It can be drawn that way, but the circuit still needs exactly one earth point, normally at the secondary star point or reference terminal, taken to the panel earth bar. Leaving it off does not remove the requirement; it moves the decision to the panel builder, which is how installations end up with a second earth at the far end of a multicore.

Does ANSI practice draw the CT differently from IEC?

The shapes differ in detail and terminal designations can follow different conventions, but the information content is the same: a primary, one or more secondaries, and a polarity reference. When a package mixes both practices, agree the convention in the drawing register before manufacture so the nameplate marking and the schematic cannot be read two ways.